The Shoal Creek Trail Is Moving Up to North Lamar

November 12, 2026
Do you want content like this delivered to your inbox?
A shaded concrete walking path curves beside live oaks and low limestone edging near an Austin neighborhood street.

Walk north on the Shoal Creek Trail out of Pease Park this month and you will spend part of the route on concrete beside four lanes of North Lamar Boulevard. For years that felt like a detour, and on paper it still is. The city's newest construction tells a different story. KUT described the five-foot sidewalk along Lamar north of 29th Street as "considered part of the Shoal Creek Trail", and every recent fix between 24th and 31st streets has widened, separated or extended that street-level path. None has reopened the creekside route below it.

That shift changes how a Central Austin resident uses the trail this winter. Here is how each stretch stands as of mid-November 2026, south to north.

Stretch Status Where you walk instead Timeline
Shoal Creek Blvd to Janet Fish Bridge, Pease Park Closed for resurfacing since April 27 West-side N. Lamar sidewalk, Shoal Creek Blvd to 29th St Estimated November 2026
24th to 29th along N. Lamar, landslide site Closed indefinitely East-side N. Lamar sidewalk South Gap in design, no construction start
29th to 31st, the Middle Gap Finished July 2026 New 12-ft path and separate bike lane on west-side Lamar Done three months early
Shoal Creek Blvd at RM 2222 Under construction Trail detour along Shoal Creek Blvd Started August 2026, through summer 2027

The Two Blocks That Already Show the Plan

The Middle Gap between 29th and 31st streets is the clearest example of what the rest of this corridor is becoming. The City of Austin's Shoal Creek Trail Connectivity Gaps project page reports that the work wrapped up in July 2026, three months ahead of schedule. Here is what changed on the ground:

  • Between 31st Street and 30½ Street, the west-side sidewalk is now a 12-foot shared-use path.
  • Between 30½ Street and 29th Street, a 10-foot terracotta bike path gives cyclists their own lane, separate from people on foot.
  • A new crosswalk on the north side of the 31st and Lamar intersection leads to the relocated bus stop at 3100 N. Lamar Blvd., and the signal push buttons are easier to reach.
  • The southbound left turn onto San Gabriel Street is closed. Drivers heading south can now turn left onto West 29th Street.
  • On the east side of Lamar, sidewalks and crossings from 31st down to the San Gabriel and 29th intersection were rebuilt.

KUT's coverage of the project explained the reasoning. The sidewalk runs along the steep cliff above Split Rock Canyon, so the extra width came out of the roadway. City data cited in that story showed an average of about 15 crashes a year on those two blocks of Lamar, and the crossing and turn-lane changes were meant to bring that number down. The project cost $1.25 million, paid for by the 2020 transportation bond and by fees developers pay for traffic impact studies.

The city also said the work would leave the existing trail through Split Rock Canyon alone. That sums up the strategy. The canyon path stays as it is, and a second route at street level is built to city urban-trail standards next to it.

South of 29th, the Same Fix Is Still on the Drawing Board

The stretch between 24th and 29th streets is where the creekside route stopped working. Landslides in May 2018 and May 2019 damaged public and private property in Pease Park, and the debris has blocked both the creek and the trail from about 26th to 27th Street ever since. The City's parks closure listing calls the 24th to 29th section along North Lamar "Closed Indefinitely." It says Austin Parks and Recreation is working with Public Works and Transportation and Public Works on improvements to the detour route east of the creek.

The long-term plan follows the Middle Gap approach. The Shoal Creek Conservancy's summary of the City's 24th–34th plan describes the South Gap as a 12-foot urban trail along the west side of North Lamar. It would run from the West 24th Street underpass to the Shoal Creek Boulevard parking lot and dog park, with better street crossings and a walking lane on the north side of the southern bridge into the lot. In October 2024 the City also added a "Lower Middle" connection to the scope, an urban trail between West 29th Street and Shoal Creek Boulevard on the west side of Lamar.

Put those pieces together and the continuous route from the 24th Street underpass to 31st Street will run along Lamar Boulevard. The Conservancy lists the South Gap as in design. The City has identified funding for South Gap construction but has not published a construction start date.

Pease Park's Paved Stretch Is Due Back This Month

The closure most likely to change your walk soon is the resurfacing between Shoal Creek Boulevard and the Janet Fish Bridge in Pease Park. It has been closed since April 27 so Austin Parks and Recreation can resurface the trail and restore accessibility. The original estimate was late June. The Shoal Creek Conservancy's closures page says permitting delays and crew availability pushed the work back, and both the Conservancy and the City now estimate a November 2026 finish.

Until it reopens, the detour is the sidewalk on the west side of North Lamar from Shoal Creek Boulevard to 29th Street. That puts the detour on the same side of Lamar as the new Middle Gap path, which turns most of the walk from the Shoal Creek Boulevard lot to 31st Street into one street-level route. When the resurfaced section opens, the paved route through the park and the street-level path along Lamar will both be usable, and you'll have a choice of route for the first time since spring.

The Conservancy's closures page and the City's facilities closure page are the two places to check before heading out.

North of the Neighborhood, the City Is Paying to Keep Trail Users Away From Traffic

The same idea is behind the largest current project on the trail, farther north where it meets FM 2222, also called RM 2222. In February 2026, Austin City Council authorized a construction contract with Austin Underground, Inc. for $3,061,232 plus a $306,124 contingency, for a total of up to $3,367,356. The project is funded by the 2020 Mobility Bond.

The project builds a grade-separated underpass so trail users can pass under the highway, linking the on-street bikeways on Shoal Creek Boulevard with the existing parkland nature trail. The contract also covers two steel encasements for future water and wastewater lines, installed beneath the trail so those lines can be upgraded later without tearing it up. According to the Council document, the underpass was named a priority during the 2019–2020 public engagement on Shoal Creek Boulevard and is a Tier I project in the City's Urban Trails Plan.

Construction started in August 2026 and is expected to run through summer 2027, with intermittent trail detours and vehicle lane closures on Shoal Creek Boulevard at 2222. The contract allows 300 calendar days.

Down at Lamar, the trail is being widened beside traffic. At 2222, it is being routed under it. Both projects are run by Austin Transportation and Public Works and paid for with 2020 bond money, and both deal with where the trail meets a major road rather than with the creek itself.

What's Still Unfunded Up on 31st Street

The North Gap, along West 31st Street between Lamar and West 34th, shows where this approach has stopped for now. The Conservancy's plan summary describes the parkland trail from the 31st Street trailhead to the Shoal Creek rock hop and gazebo as a well-loved stretch that is too steep for many people to use. The City proposes widening it to 12 feet and regrading it to meet ADA standards.

The City's project page says funding has been identified for preliminary engineering on that parkland segment and for the traffic-calming already in place on 31st Street and Shoal Creek Boulevard. Construction money for the parkland trail itself has not been identified, and neither has funding for a wider sidewalk toward Lamar. On the street, the 2021 pilot shared-use path has been removed. In its place, the city installed traffic calming and shared-lane markings, and restored the walking lane on the south curb with a low physical barrier.

Pease Park and the Conservancy Calendar Through December

With work still underway along much of the trail, Pease Park and the Shoal Creek Conservancy have a few dates on the calendar before the end of the year:

  1. Friday, November 20. The Shoal Creek Conservancy runs a volunteer cleanup on the Shoal Creek Trail. Its events page also lists rain-garden and riparian-restoration workdays through December.
  2. Sunday, December 6, 2:30 to 4:30 p.m. Pease Park Conservancy hosts a free honky-tonk two-stepping lesson and dance party with J Wagner at the Tudor Cottage and Terrace at Kingsbury Commons, 1100 Kingsbury Street. It's open to the public.
  3. Saturday, December 12, 8 to 10 a.m. Another Conservancy cleanup on the trail. Registration opens November 21, and the meeting point is emailed to registrants two days ahead.

For more on what's open along the Duval and North Loop end of Central Austin, see our Hyde Park and North Loop walk, and the Central Austin neighborhood page for a broader look at the area.

Being close to the trail is part of what people pay for on the blocks around Pease Park and North Lamar, and the trail itself is changing over the next few years. If you're weighing a home near Shoal Creek and want to know which stretches are finished and which are still years from construction, Soud Twal can go over the project timelines with you street by street. Book a Consultation.